Progress
Construction completion: Commissioning:
Line 1 96 Apartments
Construction completion:
4 quarter 2016
Commissioning:
1 quarter 2017
Ready
Line 2 88 Apartments
Construction completion:
3 quarter 2017
Commissioning:
4 quarter 2017
Ready
Line 3 160 Apartments
Construction completion:
4 quarter 2019
Commissioning:
1 quarter 2020
Ready
Line 4 96 Apartments
Construction completion:
1 quarter 2021
Commissioning:
2 quarter 2021
Ready
Line 5 144 Apartments
Construction completion:
3 quarter 2021
Commissioning:
4 quarter 2021
Ready
Line 6 117 Apartments
Construction completion:
4 quarter 2022
Commissioning:
1 quarter 2023
Ready
Line 7 133 Apartments
Construction completion:
2 quarter 2023
Commissioning:
3 quarter 2023
Ready
Line 8 124 Apartments
Construction completion:
4 quarter 2023
Commissioning:
1 quarter 2024
CHOOSE AN APARTMENT
Line 9 130 Apartments
Construction completion:
3 quarter 2025
Commissioning:
4 quarter 2025
CHOOSE AN APARTMENT
Total 1088 Apartments
Lviv, 12 Ugorska str.
FROM: 1900 $/m²
CHOOSE AN APARTMENT
(096) 2-777-333 CHOOSE AN APARTMENT Apartments
MENU
CALL +380 (44) 356 37 77
ORDER A BACK CALL
CANCEL
May 2025
Back

As of the end of May 2025, at the construction site of the Sofiyivka residential complex :

1 section:

  • Painting work is underway on the staircases and landings;
  • Tile installation continues on staircases and landings;
  • Facade work, gasification, electrical installation, installation of heating radiators – in progress;
  • The installation of elevators, entrance doors, screeds and plaster has been completed;
  • The installation of low-voltage networks to apartments has been completed;
  • The installation of water meters has been completed.

Section 2:

  • Painting work is underway on the staircases and landings;
  • Facade work, gasification, electrical installation, installation of heating radiators – in progress;
  • The installation of elevators, entrance doors, screeds and plaster has been completed;
  • Work is underway to concretize the retaining walls of the landscaping;
  • The installation of low-voltage networks to apartments has been completed.

Sections 3 and 4:

  • Landscaping work has been completed.

Office center:

  • Monolithic works have been completed;
  • The masonry of the 4th floor and parapets on the roof is underway;
  • The installation of the drainage tray in the parking lot has been completed.
Contacts
Our address:
Lviv, 12 Ugorska St.
(intersection with Vienna St.)
PLOT A ROUTE
Social networks:
Sales department:
Working hours:
Mon - Fri. 09:00-18:00
Sat: 10:00–16:00
© 2025 Sofiivka Residential Complex. All rights reserved.
Name:
Phone:
Comment:
Up