Progress
Construction completion: Commissioning:
Line 1 96 Apartments
Construction completion:
4 quarter 2016
Commissioning:
1 quarter 2017
Ready
Line 2 88 Apartments
Construction completion:
3 quarter 2017
Commissioning:
4 quarter 2017
Ready
Line 3 160 Apartments
Construction completion:
4 quarter 2019
Commissioning:
1 quarter 2020
Ready
Line 4 96 Apartments
Construction completion:
1 quarter 2021
Commissioning:
2 quarter 2021
Ready
Line 5 144 Apartments
Construction completion:
3 quarter 2021
Commissioning:
4 quarter 2021
Ready
Line 6 117 Apartments
Construction completion:
4 quarter 2022
Commissioning:
1 quarter 2023
Ready
Line 7 133 Apartments
Construction completion:
2 quarter 2023
Commissioning:
3 quarter 2023
Ready
Line 8 124 Apartments
Construction completion:
4 quarter 2023
Commissioning:
1 quarter 2024
CHOOSE AN APARTMENT
Line 9 130 Apartments
Construction completion:
3 quarter 2025
Commissioning:
4 quarter 2025
CHOOSE AN APARTMENT
Total 1088 Apartments
Lviv, 12 Ugorska str.
FROM: 1900 $/m²
CHOOSE AN APARTMENT
(096) 2-777-333 CHOOSE AN APARTMENT Apartments
MENU
CALL +380 (44) 356 37 77
ORDER A BACK CALL
CANCEL
July 2025
Back

As of the end  of July 2025,  at the construction site  of the Sofiyivka:

1 section:

  • Painting work is underway on the staircases and landings;
  • Stairs and landings are being tiled;
  • Electrical cables are being installed and circuit breakers are being installed in the apartments;
  • Work on waterproofing the courtyard parking lot (membrane system) has been completed;
  • The installation of the fire extinguishing system in the parking lot has been completed;
  • Work is underway to install parking lot lighting;
  • Installation of electrical cabinets has been completed;
  • Work is underway to improve the road and pedestrian zone;
  • Doors to the entrance and vestibule have been installed;
  • Cleaning has begun in the apartments.

Section 2:

  • Painting work is being carried out on staircases and landings;
  • The installation of radiators, electrical input switches, as well as facade work has been completed;
  • The screed work at the radiator connection points has been completed;
  • The installation of granite paving at the entrance to the parking lot from the Sofiivka and Office Center sides has been completed;
  • The improvement of the upper part of the stylobate has been completed;
  • Partial installation of gas boilers in apartments has been carried out.

Sections 3 and 4:

  • Cleaning in sections 3 and 4 is complete;
  • Commissioning of elevators is underway;
  • The building area on the Sofiivka side is open.

Office center:

  • Monolithic works, brickwork, and sloped screed on the roof have been completed;
  • Work is underway to install external sewage systems;
  • Concreting and waterproofing of the water tank has been completed.
Contacts
Our address:
Lviv, 12 Ugorska St.
(intersection with Vienna St.)
PLOT A ROUTE
Social networks:
Sales department:
Working hours:
Mon - Fri. 09:00-18:00
Sat: 10:00–16:00
© 2025 Sofiivka Residential Complex. All rights reserved.
Name:
Phone:
Comment:
Up