Progress
Construction completion: Commissioning:
Line 1 96 Apartments
Construction completion:
4 quarter 2016
Commissioning:
1 quarter 2017
Ready
Line 2 88 Apartments
Construction completion:
3 quarter 2017
Commissioning:
4 quarter 2017
Ready
Line 3 160 Apartments
Construction completion:
4 quarter 2019
Commissioning:
1 quarter 2020
Ready
Line 4 96 Apartments
Construction completion:
1 quarter 2021
Commissioning:
2 quarter 2021
Ready
Line 5 144 Apartments
Construction completion:
3 quarter 2021
Commissioning:
4 quarter 2021
Ready
Line 6 117 Apartments
Construction completion:
4 quarter 2022
Commissioning:
1 quarter 2023
Ready
Line 7 133 Apartments
Construction completion:
2 quarter 2023
Commissioning:
3 quarter 2023
Ready
Line 8 124 Apartments
Construction completion:
4 quarter 2023
Commissioning:
1 quarter 2024
CHOOSE AN APARTMENT
Line 9 130 Apartments
Construction completion:
3 quarter 2025
Commissioning:
4 quarter 2025
CHOOSE AN APARTMENT
Total 1088 Apartments
Lviv, 12 Ugorska str.
FROM: 1900 $/m²
CHOOSE AN APARTMENT
(096) 2-777-333 CHOOSE AN APARTMENT Apartments
MENU
CALL +380 (44) 356 37 77
ORDER A BACK CALL
CANCEL
June 2025
Back

As of the end  of June 2025,  at the construction site of the Sofiivka :

1 section:

  • Painting work is underway on the staircases and landings.
  • Stairs and landings are being tiled.
  • Facade work completed
  • The installation of the stylobates has been completed.
  • Electrical cables are being installed and circuit breakers are being installed in the apartments.
  • Improvement of the surrounding area has begun
  • Work has begun on installing waterproofing for the courtyard parking lot (membrane system)
  • Masonry of partitions in the parking lot has been completed, installation of fire extinguishing systems is underway

Section 2:

  • Painting work is underway on the staircases and landings.
  • The installation of radiators, electrical input devices, as well as facade work has been completed.
  • Installation of low-current networks in apartments completed
  • Concreting of the retaining walls of the improvement project has been completed
  • Laying of granite paving at the entrance to the parking lot has begun
  • Improvement work is underway.

Sections 3 and 4:

  • Cleaning has begun in 4 sections
  • Cleaning completed in 3 sections
  • Improvements near the 3rd entrance are complete
  • Silicone sealing of joints in elevator junction areas has been completed.

Office center:

  • Masonry of partitions on the 5th floor is underway
  • Masonry work on the roof completed
  • The installation of the industrial floor in the parking lot has been completed.
  • Masonry of partitions in the parking lot is being carried out
  • The main power cable is connected.
Contacts
Our address:
Lviv, 12 Ugorska St.
(intersection with Vienna St.)
PLOT A ROUTE
Social networks:
Sales department:
Working hours:
Mon - Fri. 09:00-18:00
Sat: 10:00–16:00
© 2025 Sofiivka Residential Complex. All rights reserved.
Name:
Phone:
Comment:
Up